Project Timeline Planner

Plan your demolition or earthworks project timeline, considering all implementation stages. This tool helps estimate the duration of each phase and identify key dependencies.

Enter Project Data

Typical Demolition Project Stages

Planning and Preparation

3 weeks
  • Building inventory
  • Obtaining permits
  • Documentation preparation
  • Site security

Equipment and Installation Dismantling

1 week
  • Electrical installation dismantling
  • Water and heating system dismantling
  • Removal of movable equipment
  • Window and door dismantling

Demolition Works

2 weeks
  • Demolition of internal elements
  • Roof and ceiling demolition
  • External wall demolition
  • Foundation demolition

Waste Management

1.5 weeks
  • Materials segregation
  • Waste transportation
  • Materials recycling
  • Hazardous waste disposal

Final Works

1 week
  • Site leveling
  • Cleaning works
  • Final inspection
  • Post-completion documentation

Remember that the actual project duration may vary depending on the specifics of the building, location, resource availability, and other factors.

Factors Affecting Project Duration

Building Size

Major impact - larger buildings require more time at all stages.

Technical Condition

Buildings in poor technical condition may require additional security measures and a more cautious approach.

Location

Buildings in dense urban areas require more logistical planning and may have time restrictions.

Equipment Availability

Lack of availability of appropriate equipment can delay project implementation.

Weather Conditions

Unfavorable weather conditions can extend the project timeline.

Need Support in Planning Your Project?

Our experts will help you plan and implement your demolition or earthworks project according to the highest industry standards.